Colspec was chosen to be the lead subcontractor for this project by the Main Contractor, Fletcher Construction. Our Site Manager and Quantity Surveyor worked closely with the Fletcher's Management Team for the full 12-month duration of the project, to assist in completing what was a very technical project.

We were engaged to complete and manage works including Demolition, in situ and Comflor concrete floors, structural steel, seismic joints between existing and new structures, carpentry, and cladding systems.

The exterior cladding systems specified on this project included Euro-Tray & Colorsteel metal wall cladding, shiplap weatherboard cladding to match existing, and fibre cement sheet cladding. This mixture of cladding systems was a complex install process, which resulted in a quality finish for this high profile project.

Colspec gained valuable experience working with a company of the calibre of Fletchers as a subcontractor. We formed a strong relationship with Fletchers to create a quality and efficient management team that worked together to deliver a successful project.

Jemma Cheer
Freelance graphic designer, mainly into doing logos and identity systems, but loves everything that involves thinking and looking at things.
http://jemmacheerdesign.com
Previous
Previous

Farmlands Feilding

Next
Next

Puddleducks Feilding